- A.9.2 KM of 10 km service road is complete and the remaining to be ready by this month end.
- B.15 KM of drains is complete and remaining 2.5 KM is to be ready by May 15.
- C.15 Km of Six-laining of the main road is complete and remaining to be ready by may 15.
- D.Elevated expressway is complete is by just 25%.
Hosur Road Expressway - Infrastructure project update.